The plumbing will consist of a kitchen & bathroom sink, shower, toilet, and an outdoor spicket.
The first step was for us to build the waste water pit for the bathroom.

The pit was dug about 18 feet deep and two “rooms” were constructed within the hole. PVC pipe was placed in the wall between the two rooms starting about 10 feet from the bottom.




The pipes were layed to drain into the pit. It was covered with plywood and a strong iron bar grid was constructed on top of that. This was covered with cement the same time that the floor was poured.